Name
|
Location
|
Brief Description
|
Status
|
Townes at Sullivan Trail POSH & ZAWARSKI
|
Just north of the old Laneco - abuts the Pitchfork Nursery
|
Commercial and townshouses... LOTS of them. The good news is a hardware store. Waivers applied for 4/15/04. It went before the BoS on 9/2/04. A landscape buffer was discussed between it and the Jackson farm. On 6/16/05, the BoS accepted the developer's agreements including a resolution for the traffic light at Zucksville and Sullivan Trail. Developer will pay all costs. There will be a left turn lane on Zucksville at the new light.
|
Approved by BoS 9/2/04 6/16/05 - BoS Accepted Developers Agrmnts
|
Countryside Estates Section 2 Signature Homes (1/2008) was PANNUCIO
|
Newlins Rd East at the corner of Kesslerville Rd. and just before the 90 degree bend.
|
1st time before the BoS 9/2/04. 10.64 acre tract into 21 lots. Before the PC 8/12/04 where the PC waived a geological study, requested that existing treelines stay, that street trees be planted along Newlins Rd. and that there be sidewalks on both sides of all interior streets. According to Solicitor Kline, PC 7/14/05, this plan is a very old one is therefore exempt from CR zoning open space requirements. The BoS 8/4/05 acting on recommendation from the engineer, approved the final major subdivision.
|
Preliminary Approval granted by PC (8/12/04) and BoS (9/2/04). Conditional Approval by PC and BoS with geological study waived. 5/12/05 - Tabled by PC 7/14/05 - PC Approved Final Subdivision 8/4/05 - BoS Approved
|
Practice Range - Riverview Golf Course STRAUSSER ENTERPRISES
|
AT the corner of Danser Hill Rd. and Winchester Dr.
|
This one went before the Zoning Hearing Board on August 11, 2003. Despite objections from the 3 dozen or so neighbors in the audience, a HARDSHIP variance was granted. 30 acres of farmland that was/is in the FP district is lost. This project is being touted in the local press as set to open next spring (2005) but it has yet to come before the PC or the BoS. In January (2004), during a Sunday night blizzard, the developer's crew ripped out one of the treelines. Seems he doesn't like trees.
|
Zoning Hardship Variance granted 8/11/2003
|
Towne Center II at Sullivan Trail ZAWARSKI & Posh
|
The entrance will be off of Meco Rd. behind Met-Ed. Part of the site was the Met-Ed pole yard
|
The developer plans 4 commercial lots off of Meco Rd., two on each side of Lafayette Park Drive. Lafayette Park Drive will lead into a residential project with 76 units. Access is to be ONLY from Meco Rd. On 5/12/05 Martin Zawarski presented (to the PC) several building configurations for 2 of the commercial properties (to be developed as one). He said that he met with (Forks) "staff" and they "worked it out" - the different building arrangements for the planned "flex" space. On 8/11/05 after some discussion of Impact Fees and questions by residents about who will pay for the needed traffic light at Meco and Sullivan Trail, the PC approved the preliminary & final subdivision. On 9/1/05 the BoS approved the prelim. and final subdivision and land devel. for commercial lots 2&4. There will be 3 retail/commercial bldgs. Tenants unknown but expected to be "light impact" like a Pearl Vision and/or a food place.
|
PC Conditional Preliminary Approval 10/14/04 PC Cond Appr 1/13/05 BoS Final Appr 2/3/05 5/12/05 - Tabled by PC 7/14/05 - PC - Remains tabled. 8/11/05 - PC approved preliminary & final subdivision 9/1/05 - BoS approved Lots 2&4 Preliminary & Final Subdivision and Land Development
|
Estates at Bushkill Creek (was Upstream Estates) SIGNATURE HOMES
|
The old Upstream Farms property where the dairy store was
|
26 home lots on 18 acres. The project name has changed as the former owners (Merwarth) objected to them using Upstream Farms Estates. On 10/14/04 the PC asked for an additional emergency entrance at the top (east side) of the property. The flooding on Bushkill Drive would have left this group of homes totally isolated from emergency help. The developer agreed and will install invisible blocks through a 20' easement to allow emergency vehicular access.
|
Conditional Approval by PC on 8/12/04 - Prelim Conditional Approval by BoS 8/19/04 - Final PC approval 10/14/04
|
Village at Fox Crossing (was Jacobs Farm II and also III and originally was called Adult Community - Projects A&B) Originally QUIXOTE VENTURES - 9/2006 JIM SEITZ CONSTRUCTION CO., INC. has taken over this project
|
Abutting Jacob's Farms on Kesslerville Rd. Both are north of Dixie and south of Uhlers Rd. West side of Kesslerville.
|
The developer presented plans for this project (really one project but the township has size restrictions for 55 & older communities so it was split into A&B... C is down the road a bit) to the PC for "conditional use opinion." The PC will list 'conditions' for the BoS to consider... no driveways on the new through road, Braden Rd. And, Braden Rd., since it's mandated in the township master plan, must be up to the township specs. The PC is concerned about safety issues with this main road through a 55 & older community but the road is the township's idea and not the developer's. This is to be yet another community of MANUFACTURED homes. The interior roads will be owned by the developer and the main road by the township. This project has approx. 180 homes on 35 acres. 10 more acres will be included in a future phase. The developer presented a sketch plan to the PC on 10/13/05 and parcel C is no longer included as it was sold to one of the neighboring property owners (BetcoBlack?). The project will have 7 acres of open space and the developer will do a "traffic report." The developer will work with the developer of Fort James III (across Kesslerville from it) to solve the flooding problem there. The units along the collector road, Braden, will not front on it. This is now one project and is no longer split into sections A & B. On 3/9/06 the PC, after a preliminary presentation, voted 7:0 to table the project pending Hay's review letter. There will be 135 units in phase 2 and it will have landscaping buffers. Braden Drive will have sidewalks. On 6/8/06 the PC reviewed this plan again. There was much discussion of sidewalks to keep the residents from walking in the street. Braden will be a treed boulevard. The developer requested the same waivers that were granted in Jacobs Farm I: Roadway widths (vote 5:1), Geology study (6:0), Rec paths (6:0), Sidewalks except for Braden and additional sidewalks on the west side from Biltmore #2 south to the clubhouse (6:0), and two other waivers (also granted). The detention ponds will be mow-able. Conditional approval was granted 6:0. On 9/14/06 Hay explained that there is a new owner for this phase of the development and that a club house will be built for it. Hay also said that the plans have changed. The developer was not present and the plan was tabled 7:0. Both Turner and Wideman want more sidewalks. Chuss wants more off-street parking because the roads are too narrow. On 10/12/06 the PC learned that Jim Seitz Construction Co., Inc is the new owner of this project. Sidewalks will be installed on the entire length of and on both sides of Biltmore Avenue and it will have its own clubhouse. They learned too, from David Lear, PE, that "older people tend to complain a little more." This was in reference to complaints about on- street parking from residents in Phase I. Phase II will have "no parking" signs. The final major subdivision was approved in a 7:0 vote. On 10/19/06, the BoS approved the final plan. Howell asked if the developer if there will be a tot-lot for the residents' visiting families. Seitz said that there is room for one behind the clubhouse. On 5/10/07 the developer presented a new "phasing" plan to the PC. Sixty lots and Braden Blvd. will be in phase I. Phase II will have 75 lots. Lots 6 & 7 will be temporary parking until phase II is started. The northern detention basin will also be included in phase I. The PC granted conditional approval. On 5/17/07 the BoS approved the new phasing plan in a 5:0 vote. Nicholas and Ackerman asked that the developer revisit the grass in Braden Boulevard. They do not want to send township crews there to mow it. On 9/20/07 Kline told the BoS that all paperwork is in order including a $2,803,833.86 Letter of Credit. The Developer's Agreements were approved in a 4:0 vote.
|
9/9/04 to PC for conditional use opinion. 2/3/05 Conditional Use granted BoS. 10/13/05 - PC reviewed sketch plan 3/9/06 - Preliminary presentation to the PC - Tabled 6/8/06 - PC Conditional approval 7/6/06 - BoS granted conditional approval to land development plan 9/14/06 - PC Tabled 10/12/06 - PC approved final major subdivision 10/19/06 - BoS approved Final Plan 5/10/07 - PC - Phasing Plan for JF2 given conditional approval 5/17/07 - BoS approved phasing plan 9/20/07 - BoS approved Developer's Agreements
|
Forks Landing Business Park RB Associates
|
East side of Sullivan Trail, north of Uhlers and mostly north of the RR tracks
|
This encompasses 37 acres in the EC district. There are no lots sold yet. PennDot is requiring traffic signals on 115. A storm line will go under the Norfolk Southern tracks that will drain the site into the Bushkill swale. The DEP and Army Corp. will issue permits for this. The township will not take over the storm line. On 1/12/06 the developer presented a modified plan eliminating 2 of the 5 planned lots (same acreage, fewer lots) because of the cost of the necessary intersection and road improvements. There will now be one very large lot and two with Sullivan Trail frontage, as well as a shorter cul-de-sac. The really big lot will likely have a warehouse facility on it. The PC allowed that the "permanent" paved emergency access to the rear lot can be deferred provided that temporary emergency access is provided to each of the front two lots. Tabled by PC 3/9/06. On 9/14/06 the PC granted conditional approval to the final major subdivision plan. There will be three lots and a side-walked cul de sac. The developer granted a time extension so that the plan can be presented to the BoS at their first October meeting. The BoS granted conditional approval to the plan on 10/19/06 in a 4:0 vote (Nicholas was delayed in traffic.) Sullivan Trail will be widened on both sides in the right-of-way(s).
|
9/16/04 BoS granted Preliminary Conditional Approval 1/12/06 - PC tabled 3/9/06 - PC tabled 9/14/06 - PC - conditional approval 10/19/06 - BoS granted approval
|
Sullivan Trail Commercial Development Robert Irons, PE
|
Old LANECO property
|
A sketch plan was presented to the PC showing only commercial properties on this site. The rear 3 acres (abutting the township park) will be dedicated/given to the township. It includes the storm water basin. The PC suggests a sidewalk to get the kids from Sullivan Trail to the daycare safely and a sidewalk all along the Sullivan Trail frontage. The developer will do the Sullivan Trail sidewalk for sure. The other is more problematic since there is another property owner involved. On 6/9/05 the developer, One Up LLC, presented a proposed final configuration for the parcel, a fast food restaurant, a bank, and retail space where the old Laneco now stands. The PC objected to an entrance to the fast food restaurant from Sullivan Trail (southbound traffic only) and suggested ways to reconfigure the plan to allow better traffic flow through the parcel. A way to get kids safely from their bus stop on Sullivan Trail to the daycare center in the back of the lot is still an issue. The developer failed to attend the 7/14/05 PC meeting and the plan was rejected. The developer's representative did appear at the 7/21/05 BoS meeting and based on a letter by Twp Eng Fred Hay, approved the "preliminary/final" plan. Hay made a cursory reference to the "rejection" by the PC but it was not discussed. The Recreation Fees were "exchanged" for a 2.7+/- acre donation of the land behind the old Laneco (including the basin). The Twp will get all other fees. It was agreed that the Twp and the developer "will work something out" regarding getting the kids safely from the Sullivan Trail bus stop to the daycare.
|
10/14/04 PC reviewed sketch plan. 2/10/05 - Tabled by PC 4/14/05 - Tabled by PC 5/12/05 - Tabled by PC 6/9/05 - Dev. granted a 30 day extension - PC Tabled 7/14/05 - No show at PC by developer - PC rejected plan 7/21/05 - BoS approved Preliminary/Final based on letter Hay letter 6/3/05
|
College Park (was Farm View Estates) Signature Homes
|
Off of Zucksville Road and adjacent to the Community Park. Sycamore St. is the southern boarder. Wagonwheel will bisect.
|
Presented to PC for Preliminary Subdivision. PC doesn't like the NAME and asked the reps. to find another... not "College, not Sullivan and NOT Bushkill!" The PC was shown a plan with 68 lots containing 65 single family dwelling "units." The developer is dedicating the portion adjacent to the park to the Township in lieu of recreation fees. The plan showed 2 flag lots and 3 homes with driveways onto Zucksville Rd. The PC said "NO driveways on Zucksville no matter what PennDot says." The waiver for the flag lots was denied. On March 18, 2004 the BoS saw a sketch for this project and did NOT like the flag lots either. The existing farm buildings will stay. Developer was asked to return next month with another layout. March 10, 2005 PC shown new Preliminary Final subdivision without flag lots and without driveways on to Zucksville Road. There is one cul-de-sac. A SALDO waiver for the new Betty Lane was granted. Betty Lane does not form a 90 degree intersection with Wagonwheel. On 2/16/06 Kline reported to the BoS that all was in order - a $2.3 million Letter of Credit in place, and 5 acres adjacent to the Community Park to be deeded to the Township. The developer's agreements were approved 5:0.
|
11/9/04 Tabled by PC 2/10/05 - Final Plan tabled by PC. 3/10/05 - PC approved Preliminary Final Subdivision 3/17/05 - BoS approved Preliminary Final Subdivision 2/16/06 - BoS approved Developer's Agrmnts
|
Tioga Pipe & Fort James II Jalapeneaux, Inc G&G Developers LLC
|
Kuebler Road across from Harvel Plastics
|
PC - Industrial building for steel pipe warehouse and distributorship. It will be an expansion of an existing Philadelphia based business. The company plans 26 jobs and 10-12 inbound deliveries per day as they stock the facility. They expect to ship 3 loads outbound per day. The hours of operation will be 7 AM to 7 PM. There will be inside storage as well as outside storage. The outside racks will be 14 ft. high. There will be a cutting shed attached to the main building. On 6/16/05 the BoS approved the developer's agreements for the Tioga Pipe lot as well as the agreements for the Fort James II Subdivision. On 5/11/06 the PC conditionally approved (7:0) the land development for lot 2C, future home of an adhesives company that will employ 10-15. The building is proposed to be 25,000 sq ft and will be used for light manufacturing. The developer has agreed to install sidewalk along all of their property fronting Kuebler Road but it will be done all at one time. On 5/18/06 the BoS took two votes, one on the sidewalk installation (when other lots are developed) on Kuebler Road and another on the plan. Both votes were 5:0.
|
11/9/04 Conditional Approval by PC. 11/18/04 Conditional Prelim. Approval by BoS 2/10/09 - PC approval of Final Subdivision plan. 2/17/05 - BoS Final Plan approval 6/16/05 - BoS Approved Developer's Agrmnts 5/11/06 - PC gave conditional approval of the land development for Lot 2C, an adhesives company. 5/18/06 - BoS approved 6/5/08 - BoS accepted Mort Drive
|
Riverview Estates West Segal & Morel
|
Off of Newlins Road East
|
Phase I final subdivision presented to PC. 51 of the 221 lots are in this phase. It will involve building more of Winchester Dr. but will not connect through until Phase 2. Currently the massive swale is under construction. The developer will install the same street lights as the adjacent Riverview projects. The treeline on the southern edge will stay. The bike path will connect. The final plan for Phase I was approved by the BoS with the condition that Winchester Drive will be the ONLY construction entrance. On 5/12/05 Dean Turner, PC, said that he was contacted by a resident and advised that the "drain" is not working. The resident will provide photos to Turner who will then get them to Hay (Township Engineer). On 6/9/05 we learned that the residents on the north side of Newlins Road will be able to hook up to the new sewer line. On 6/16/05 the BoS granted Final Plan approval for Phase 2. All is in order to start the infrastructure work. On 8/10/06 engineer Hay told the PC that Phase III was just submitted and he has yet to look at it. It was tabled. Phase III, final subdivision was approved by the PC on 10/12/06. The developer asked that the opening of Winchester Drive (to Vista Estates) be delayed until more construction is completed. Hay recommended this as well. Phase I is completed and the infrastructure for Phase II is done. PC approved final subdivision for Phase III in a 7:0 vote. On 10/19/06 Hay told the BoS that this was a totally clean plan. It was approved in a 5:0 vote. Winchester Drive will remain closed through to Vista Estates until the construction is done.
|
11/9/04 PC - Final Approval Phase I 12/2/04 - Final Plan Phase I approval BoS 2/10/05 - Phase II tabled by PC. 4/14/05 - Phase 2 tabled by PC. 5/12/05 - Phase 2 tabled by PC - time extension to 12/25 6/9/05 - Phase 2 Final Subdivision approved by PC 6/16/05 - Phase 2 Final Plan and Developer's Agrmnts approved by BoS 5/4/06 - BoS approval of Phase 2 Developer's Agreements 8/10/06 - PC tabled Phase III 10/12/06 - PC approved Phase III final subdivision 10/19/06 - BoS approved final plan
|
Forks Village - Phase I, II, & III Calantoni
|
Between Sullivan Trail and Kesslerville Road across from Kuebler and extending south
|
This is the first phase of a much larger (and long planned) development. Phase I consists of 26 townhomes and 12 twins. The interior street names are North Fork Drive, South Fork Drive and Fieldstone Trail (which will connect Kesslerville and Sullivan Trail). The project will begin with North Fork Drive and because it will not be the whole development, there will be a non-conforming, temporary cul-de-sac. Escrow is recommended for part of South Fork Dr. It's an older plan and NOT subject to the current sinkhole requirements. On 8/18/05 the BoS approved the Developer's Agreements. This allows the developer to proceed under an indemnification agreement. On 4/13/06 phases 2 & 3 were before the PC. The developer had no issues with Hay's letter. These phases will have 57 two story apartments (each unit will have 2 floors) and 55 townhouses. The project total is 150 units. The lots over the gas line are buildable, there will be sidewalks on both sides, and the homeowners association will own the open space. Turner asked that the open space NOT become a cattle corral with a fence all around it. A landscaping plan will be presented at their next appearance. It was tabled 6:0. On 6/8/06 the PC learned that all PennDot approvals were received in 2004. Kline reminded the developer that they agreed to "no" fencing in the open areas. It will be added as a deed restriction. The plan was given preliminary conditional approval 6:0.
|
12/9/04 PC - Final Subdivision approved with conditions in engineers' letter. 2/3/05 BoS - Final Subdivision Approval. 8/18/05 - BoS Developer's Agrmts. 4/13/06 - PC - tabled Final Subdivision 6/8/06 - PC - final conditional approval 7/20/06 - BoS - final conditional approval 8/3/06 - BoS - Developers Agreements accepted 11/16/2006 - BoS accepted developer's agreements - Phase 2
|
|
|
|
|
|
Penn's Ridge Hornstein Enterprises
|
|
|
|
From Zucksville Road to Bushkill Drive. An older, ongoing development.
|
Report given by Hornstein of the next phase in this ongoing project. It includes the Kesslerville Road extension to Bushkill Drive which is nearly complete. The next phase will include 154 2 story condos. The project was initially approved with rental apartment units. The interior roads will be maintained by the condo association. Les Ottenwalder (PC) and Bonnie Nicholas (BoS) expressed disapproval of the dead end(s) in this phase. Phases 9 & 11 given final approval by BoS on 6/16/05. The Developer's Agreements were accepted by the Board on 7/7/05. On 8/18/05 the Developer's Agreements were approved by the BoS. David Howell asked that the developer consider putting in open space for the children to play. On 2/9/06 the PC viewed and discussed the conceptual plan for 102 condominiums. The developer has abandoned plans for apartments and what was shown represents the end of the dwelling units in Penn's Ridge. There is still commercial area to be developed as well as the completion of the bike path. Howell asked the developer if there will be restrictions placed on rentals, that is investors buying so that they can rent them. He was told that the contract that is in draft form right now requires substantial notice and a first buy-back provision by the developer or later on, the homeowners association. On 5/10/07 the developer presented a sketch plan for discussion to the PC. Originally this was to be 164 apartments but the "market changed" for townhouses and condominiums. The developer changed the plans. These phases will now have 102 townhouses and condos for a total site build-out of 540 units. There will be a 3 acre open space area as well as a 3 acre (not yet presented) commercial area. Phases 13 & 14 units will be "more upscale" and the roadways will be lined with Belgian block. Most buildings will have 4. 5, & 6 units. There will be four 10 unit "flat" (one floor units) buildings. These will have 1-car garages under the buildings. There will be sidewalks on both sides of the street and parking will be limited to one side. There is a homeowners' association already in place. The sketch was given tentative approval. On 5/17/07 the BoS approved moving the sewer easement for phases 9 & 11 in a 5:0 vote. They also saw and discussed the sketch plan for phases 13 & 14 (detailed above). On 7/12/07 the PC tabled in a 4:0 vote the final subdivision plan for phases 13 & 14. Chairman Erik Chuss remarked that the "density is just disturbing... " Rumors to the contrary, Penn's Ridge is not keeping RCN out of the project. RCN declined to come in when invited for phases 9, 11, 13, & 14. RCN said that they would have to tear up too much roadway to get to the new areas. Penn's Ridge will provide the Township with RCN's letter. Read Mathias (Morning Call) for more. On 9/13/07 the PC approved the final subdivision plans for the last residential phases, 13 & 14. The final plan for the commercial land development was also presented and it was tabled. The plan calls for a 10,000 sq ft neighborhood commercial center tucked into the hill along Bushkill Dr. The bikepath will cross Bushkill Drive, weave through the trees and connect with the Palmer path. The crossing will require a PennDot permit. Planner Carl Dicker suggested that the huge retaining wall behind te building be terraced to soften its look. Tamborrino suggested that parking directly in front of the building be redesigned as allowing it will cut of egress and ingress to the site. On 10/4/07, the BoS approved the final plan for phases 13 & 14. This will bring the residential build out to an end at 540 units. On 10/11/07 the PC saw a revised commercial land development plan. There was discussion about the near sheer wall behind the building with suggestions by the PC to break it up with terraces and landscaping. The PC learned that there may be as many as three businesses in the building and requested that it given a country store look - much like the old Upstream Farm store had. Photos of other commercial properties were shown by the developer and all agreed that the look of the new Palmer Nursery is preferred to the other, more contemporary looks. On 11/8/07 the developer was back before the PC to show what they thought the PC wanted for a terraced retaining wall behind the retail building. Not. Tamborrino observed that with the 6' depth on each level, it will still look like a massive shear wall from the road. The shallowness does not allow for tree plantings, only shrubs and other plants. Turner said that there is at least room for vegetation. The developer said that even though this project is exempt from the new zoning ordinance, they are trying to design within the spirit of the "heritage corridor parameters." The PC has asked for a time extension so that the developer can come back with (rendering) elevations. A time extension until January 30, 2008 was granted by the developer. They will be back at the December 13 PC meeting with more "courtesy views." Action was tabled in a 7:0 vote. The 12/13/07 PC meeting was cancelled due to the weather. On 1/10/08, the PC saw architect's renderings of a commercial building. It was well received and the developer was asked to "commit to the style, pitched roof, and elevations presented." Another condition is that the plantings be indigenous to the Bushkill corridor. The developer agreed to both conditions. Weis will provide a contact at the Bushkill Conservancy to the developer so that they can get a list of appropriate plants. The concept was approved 5:1 with Georgeann Wambold casting the dissenting vote. On 1/17/08, the Bos saw the commercial concept renderings. After discussion of the project history, the planned bike path, landscaping, and the look of the building, the BoS asked the developer for an extension so that they could review the not-yet-approved PC minutes and recommendation. The project was on the weather-cancelled 12/13/08 PC meeting agenda. The developer agreed to grant an extension until 2/22/08. The plan will be before the BoS at its 2/21/08 meeting. And, on 2/21/2008, the BoS approved the plan subject to all conditions noted by the PC and to Hay's letter.
|
2/10/05 - PC heard report of next phase. 2/17/05 - BoS Sketch Plan approval. 5/12/05 - PC tabled Phase 9 & 11 (Final Major Subdivision) 6/9/05 - PC approved Final Major Subdivision 6/16/05 - BoS Final Approval 7/7/05 - BoS Accepted Developers Agreement 8/18/05 - BoS Accepted Developers Agreements 2/9/06 - PC was shown the Conceptual Plan for condominumns - no action was taken 11/16/06 - BoS accepted roads - phases 5-8 5/10/07 - PC saw sketch plan for phases 13 & 14 5/17/07 - BoS approved sewer easement for phases 9&11 - 5:0 vote 5/17/07 - BoS saw sketch plan for phases 13 & 14 7/12/07 - PC tabled final subdivision 9/13/07 - PC approved final phase of residential Phases 13 & 14 9/13/07 - PC Tabled final plan commercial 10/4/07 - BoS approved final plan of residential Phases 13 & 14 10/11/07 - PC - revised commercial land development presented 11/8/07 - PC - another revised commercial land development presented - Tabled 1/10/08 - PC saw renderings of commercial building concept - conditional approval granted 1/17/08 - BoS accepted extension - commercial land development - pending receipt of PC minutes from 1/10/08 - Tabled until 2/21/08 2/21/08 - BoS approved
|
Sterling Hill Estates JIM SEITZ CONSTRUCTION CO, INC
|
Southwest corner of Mitman and Arndt roads. Was the 69 acre Seifert Farm and is in the CR zoning district.
|
Seitz is planning 135 single family lots. The new streets will have sidewalks on both sides and there will be a concrete bike path around the outside of site (a condition). There will be NO open space in this development. Seitz opted to pay the Recreation Fees instead. Another condition is safe school bus stops. The developer will be guided by the EASD when siting them. It was also requested that there be a snow easement (a place designated for snow piling) in the cul de sac. On 3/3/05, BoS recommended that LACK of open space and recreation area be reconsidered by developer. They learned that there are no driveways planned for Arndt Road and that there will be 4 common ones on Mitman. Tabled by PC on 9/8/05 - no one from the developer was at the meeting. On 10/13/05, Hay said that his office is still reviewing the project. It was tabled in a 4:0 vote. The developer was a no-show at the 11/10/05 and because a time extension would be needed, the PC had to reject the plan. On 12/8/05 the PC rejected in a 2:4 vote, the final subdivision plan. The developer agreed to all the conditions in the engineer's report, they widened the sidewalk for a school kid pick-up area on Arndt Rd., they added a street light at the pick/up point, they said that the private detention ponds would be maintained by a homeowners association, and agreed to submit their landscaping plan to the engineer for approval. No reason was given for the disapproval. This plan will likely go to the BoS anyway only without approval of the PC. On 1/19/06 after Kline explained that the preliminary plan was approved and "you can't just remove that," the Bos approved the final plan in a 5:0 vote. The developer's engineer and lawyer were there. There will be a "tot lot" and a homeowners' association.
|
2/10/05 - PC granted Conditional Approval. Dean Turner voted NAY and Erik Chuss abstained. See MCall for more details. 3/3/05 - BoS Accepted Prelim Subdivision w/ conditions. See Express Times. 9/8/05 - PC Tabled 10/13/05 - PC - Tabled. 11/10/05 - PC Rejected 12/8/05 - PC rejected final subdivision 1/19/2006 - BoS approved Final Plan
|
Richards Drive-in Lou Ferrone, PE
|
The Falk Firehouse property on Sullivan Trail adjoining the new Municipal Complex.
|
The owners of Richards Drive-in in Palmer Township want to erect a 20 seat restaurant on the lot owned by Falk. It would not be a drive-in restaurant but will have a walk-up window. The existing lot will be subdivided (for this project). The PC suggested making the new lot larger to allow ample parking and to make it "stand on its own." They also suggested that a permanent easement be created to allow the sharing of the entrance/exit onto Sullivan Trail. PC approved minor subdivision with the old easements as conditions on 8/11/05. The BoS approved it with the same conditions on 9/1/05
|
5/12/05 - PC Minor Subdivision Tabled 6/9/05 - Dev. granted 90 day extension - Tabled 7/14/05 - PC saw revised plan - Remains Tabled 8/11/05 - PC approved with conditions 9/1/05 - BoS approved with conditions
|
Forks Medical Office Building Warren Hospital & Palmer Family Practice Sullivan Trail Business Park
|
Located in the commercial parcel being developed by Goffredo off of Uhlers Road. It is on the new Braden Boulevard.
|
The hospital (as well as a local bank) have been unable to push the developer, Goffredo, to finish the site improvements. As a result, the PC imposed a condition on the hospital project that "no building permits" will be issued until all site improvements are done and approved by the Township engineer. Another condition is that a "contribution" will be made towards finishing/extending the road. The building will be 18500 sq. ft. and will house medical offices, the Palmer Family Practice, an imaging center, etc. The PC recommended sidewalks on both sides of the street.
|
5/12/05 - PC Preliminary Final Approval 7/7/05 - BoS Conditional Final Approval
|
Riverview Recreation Center & other Riverview projects Strausser Enterprises
|
Located south of Newlins Road and behind the new homes along Iron Lane. Adjacent to the bike trail.
|
This is the private recreation center promised by Strausser Enterprises to the new residents of Riverview Estates. It is a 4-1/2 acre subdivision of a 25 acre site. Under discussion at the PC 6/9/05 was the location and ownership of the main entrance road, whether it will be part of the subdivision or remain with the main parcel. The Conditional Use Hearing will be in July. Tabled by PC on 8/11/05 when Hay said his office is waiting for revised plans. At PC on 9/8/05 Conditional Preliminary Approval was granted. Also, it was announced by Strausser's representatives that the Village (commercial & residential mix) proposed for the adjacent 21 acres is now formally withdrawn "at this time." They will either go ahead with a traditional housing development or "maybe another concept." On 10/20/2005, the BoS granted conditional use and included the letter from Keystone Engineering as the conditions. The BoS asked too for a "snow" easement. On 11/10/05, Panto showed a revised sketch plan (large file) to the PC during an impromtu Comments session near the meeting's end. Kline advised him that if Strausser wanted to relocate the road into the recreation facility, new plans must be submitted. On 12/8/05 Lehigh Engineering and Panto presented the plot plan that was originally shown in April as a sketch. It now shows a temporary road entrance over part of the cul-de-sac. They were told that they need not build the cul-de-sac (right away?) but will have to provide security for it. It was approved in a 5:0 vote. On 1/19/06 Panto told the BoS that the cul-de-sac will remain where originally drawn and that it actually works better for the many ideas they have for the rest of that area. Hay pronounced it a clean plan (just waiting for some outside approvals.) The cul-de-sac will not be built until they do the rest of the parcel and when built will remain private and owned by the homeowners association. No snow easement will be necessary. The driveway that will be constructed first will lead to the parking area. The site will have a bath house, a swimming pool, basketball, tennis and sand volley ball courts, a pavilion, open space, and a parking lot. Final Plan approval was granted in a 5:0 vote. - On 7/13/06 the PC approved a request by Strausser's representatives for a temporary parking lot near the golf course's newly constructed pavilion. It was learned too that Strausser plans to open the Winchester Drive storm grates soon even though their promised drain under 611 has not been constructed. According to Sal Panto, the water will flow from their stormwater drain system directly into the Frost Hollow swale. The new pipe to the Delaware River will be built in about a year when the intersection improvements - including widening a bridge by 12' and adding two left turn lanes - are undertaken. - On 9/7/06 Development Extensions To Extend Phases 5 & 6, Maintenance Building and Bed & Breakfast was on the BoS agenda. Engineer Hay said that he has given the solicitor's office a list of 5 or 6 items to be completed. Solicitor Steven Goudsouzian said that he will draft a resolution for the Board's review. The extensions will be discussed after the resolution is prepared. On 9/21/06 the BoS received a copy of the solicitor prepared resolution. Strausser's signature will be sought before voting on it. Their escrow account must be funded and other project phases must be completed before a time extension will be granted so that the zoning does not revert back to CR (Country Residential). If it does, the density allowed will change. On 4/12/07, the PC tabled in a 5:0 vote, the Final Subdivision plan for a Strausser part of Riverview Estates. Phase VI is for townhouses along Winchester Drive between Broadway and the clubhouse trailers. There was neither a letter form the engineer nor a representative from Stausser Enterprises in attendance. Kline stated that all final plans were to have been submitted to the Township by April 20, 2006. He noted that plans for phases 4A (the country inn), 5 (the clubhouse?), and 6 (the townhouses on Winchester) failed to make the deadline. Kline will suggest to the BoS that they give the developer 6 months (until October) to clean up everything that the Township wants cleaned up and then give an additional 6 months to submit the plans. Kline said that if this is not done, Strausser may lose the right to build any of these phases - the PRD will be thrown out of the window, everything will be subject to the new zoning ordinance, and only single family homes will be allowed on Winchester Drive. If the current final plan is not withdrawn, the clock starts ticking (toward that end.) Among the incomplete items are the punchlists for phases 2, 2A, 2C, 3, and 4. In addition, the developer's agreements are not signed for the work on the 611, the deed to the Township for the pumping station land has not been handed over, the escrow accounts are "six figures" in arrears, and the letters of credit need to be renewed. Whew! Sal Panto was invited by John Ackerman to appear at the 4/19/07 Board meeting to discuss the construction easement for work on the Rte. 611 and Frost Hollow intersection. Panto explained that an easement agreement was worked out with Mr. Soda and that the Board's help would not be needed. Panto said that with DEP modification of the permit, work may start in 45 to 90 days. The conditions of time extension resolution that the Board expected to adopt that evening was tabled because Strausser's attorney was unable to attend. It is rescheduled for a vote at the May 1st meeting. On 5/3/07, Kline reported that all the paperwork was in order, monies in escrow, etc. for the Recreation Center developer's agreements. They were accepted in a 4:0 vote - Nicholas was absent. On 5/10/07, Kline explained to the PC that because of incomplete items, he was preparing a resolution for the Board basically giving Strausser Enterprises an ultimatum - finish everything, catch up the monies owed, or lose the right to build under the old zoning. Phase VI was on the agenda. The PC voted to recommend that it be withdrawn as the planning "clock is ticking." On 5/17/07 the BoS approved the resolution that makes further approvals for phases conditional on the completion of all unfinished work and the payment of all unpaid monies due the Township. If the conditions are not met by the end of November 2007, the developer loses the right to the PRD (Planned Residential Development)... no townhouses on Winchester Drive! On 6/14/07, Weis informed the PC that Strausser has withdrawn the Phase VI plans. This was needed in order to :"stop the clock" so that the other terms of the resolution could be completed without further penalties. On 8/16/07 the BoS listened to Strausser attorney Gary Asteak tell them that the tree cutting on Old River Road of old stately maples owned by the Township was "implicit" in the Township approved plans for intersection improvements to Frost Hollow and Rte. 611. Please read Jimmy Miller (Express Times) and Madeleine Mathias (Morning Call) for more. Also see the FAC blog meeting notes and the post "Did You Hear The Trees Scream?" There are photos of the tree destruction in both blog posts. On 11/8/07, during the presentation by Hay of the revised phasing plan for Riverview, the PC learned that Kline is "in discussions" with Strausser. Of the phasing plan change, Hay said that it was in response to residents to get Winchester paved. The line change to the north side of Winchester was approved in a 7:0 vote. The recreation path was also discussed. The PC agreed to let the Recreation & Trails comp plan subcommittee review it and make a recommendation. Kline said that the Township learned a lesson - sidewalks should be required on both sides of streets. Action was tabled in a 7:0 vote.
|
6/9/05 - Subdivision and Land Development PC Approved 3:2 7/14/05 - PC - Granted time extension - Remains tabled 8/11/05 - PC tabled 9/8/05 - PC granted Conditional Preliminary Approval 10/20/05 - BoS granted Conditional Use 11/10/05 - Sketch re-shown to PC "unofficially" 12/8/2005 - PC approved Land Development or Final Conditional Use 1/19/06 - BoS approved Final Plan 8/3/06 - BoS Developers Agreements accepted ............... 7/13/06 - PC approved request for temporary pavilion parking 8/3/06 - BoS approved temporary pavilion parking .............. 9/7/06 - BoS tabled discussion phases 5 & 6 9/21/06 - BoS to consider Resolution to compel completion of other phases 4/12/07 - PC tabled Phase VI Final Land Development 4/19/07 - BoS tabled time extension resolution .............. 5/3/07 - BoS accepted developer's agreements for Rec Ctr .............. 5/10/07 - PC recommends withdrawal of Phase 6 plan 5/17/07 - BoS votes for resolution 5:0 6/14/07 - PC notified that Phase VI plan was withdrawn ............... 8/16/07 - BoS considering remedy for Township tree cutting ................ 11/8/07 - PC approved revised phasing plan
|
Knollwood Estates Phase I Nic Zawarski & Sons
|
On the north side of Zucksville Road near Ben Jon Road.
|
This development consists of 40 single family homes. Developers agreements okayed by Solicitor Kline (BoS) 4/7/05. Letter of Credit ($1.084,098) and all paperwork in order 5/5/05 BoS. BoS approved an ammendment to Phase I on 12/15/05. Ben Jon Road will be rebuilt by the developer and the Township will return the $28K deposit.
|
4/8/04 - PC Conditional Final approval. 4/7/05 - BoS approved developers agreements 5/5/05 - BoS - per Kline Letter of Credit rcvd. 12/15/05 - BoS approved ammendment
|
Knollwood Estates Phase 2 Nic Zawarski & Sons
|
Behind the Gertner Farm at Mitman & Zucksville
|
Preliminary subdivision of 113 homes - Received by Engineer and under review 5/12/05. Before the PC on 7/14/05. Developer granted an extension to 9/10/05. On PC agenda 8/11/05 but Hay said that his office is waiting for revised plans. Tabled. On 9/8/05 at PC mtg, Hay said that an extension was granted and that his office is still awaiting revised drawings. The project remains tabled. At 10/13/05 PC meeting, Hay said that his office is still awaiting revised drawings and the project remains tabled. At PC on 12/8/05, the engineer recommended that it remain tabled. On 1/12/06 the PC in an unusual move, voted to reject the time extension offered by the developer (to 4/27/06) based on Hay's letter from the summer 2005 . It will now go to the BoS for acceptance or rejection of the time extension. If rejected by the BoS, the developer must resubmit the plans in order to go forward. On 1/19/06 the developer and his representatives appeared before the BoS to ask that the time extension be granted. It was explained that the project holdup is a result of DEP scrutiny because they must put a culvert crossing in the 100 year flood plain. The DEP must approve it. They said too that the fish commission suggested a fish ladder. Ackerman said he'd never seen fish swim in grass. PennDot is requiring additional culverts to Bushkill Stream. Open space is being provided along the swale and they will continue Mitman Road as per the Comprehensive Plan. The time extension was granted in a 5:0 vote. The PC tabled this 2/9/06 pending receipt of revised drawings. The developer did offer that the adjacent land to the north (in Plainfield Township) of their project has been sold to a "reasonably large developer." On 5/11/06 the PC voted 5:2 (Turner & Chuss) to approve the subdivision. There will be no water detention area in the 100 year flood plain because it's necessary that the water pass through the site quickly on its way to Bushkill Creek. The open space will be turned over to the homeowners association and will be kept in a natural state. There will be sidewalks throughout. The BoS vote on 5/18/06 was 4:1 with Nicholas voting nay. Her concern was with the 100 year flood plan and lack of a real second exit road in the event of flooding. The plans are to use the road surface for Ben Jon (no longer a Township road) for emergency access since it still has a road subsurface. On 10/12/06 the PC agreed to Table this plan. That action moves it forward to the township engineer, Fred Hay, for review. Hay distributed a printout from the FEMA website containing a definition of a "100-year flood." Hay noted Supervisor Nicholas' concerns about the road as a violation of the greenway agreement. He explained that a box culvert bridge is not considered development. He added that it is big enough to drive a car through. Terry Zawarski appeared before the PC on 11/9/06 and took exception to additional comments added by Hay after the conditions of the conditional approval had been met. Hay included on the list that he would like to see the plans for the storm sewer improvements. Zawarski would too since apparently at this point, they have not been designed by PennDot. Whatever they are, PennDot is to provide the materials and Zawarski the labor to improve the storm drainage at the Zucksville/Bushkill intersection. Hay agreed to eliminate the comment. Both the developer and the Township (Hay) will press PennDot for plans. The other "new" (and contested) item on the engineer's letter was for bikepath continuity through Phase 2. Zawarski said that Don Miller helped design one for Phase 1 where it was a "condition" and that it was not an issue for Phase 2. He said that they are putting sidewalks on both sides of all streets because they want to and not because they have to and he thinks that a bikepath between 2 properties will decrease each lot's value. The PC will recommend to the Board that one be included. Tamborrino said that "Don Miller will decide." Hay asked too that the Two Rivers Greenway Plan be considered by the developer. Zawarski had never heard of it but agreed to consider it. On 12/7/06, after much discussion of the bikepaths and reminders by the developer's attorney and engineer that Zawarski is putting sidewalks in on both sides of each street even though they are not required to be on both sides (subject to interpretation according to Hay), the Board gave conditional approval of the Final Plan in a 4:0 vote.
|
5/12/05 - PC - Hay said under review 7/14/05 - PC tabled - extension granted. 8/11/05 - PC tabled 9/8/05 - PC - Remains tabled 10/13/05 - PC - Remains tabled 12/8/05 - PC - Remains tabled 1/12/06 - PC rejected time extension 1/19/06 - BoS accepted the time extension 2/9/06 - PC tabled 5/11/06 - PC approved preliminary subdivision 5/18/06 - BoS approved Preliminary Plan 10/12/06 - PC accepted (for engineer's review) the final major subdivision 11/09/06 - PC accepted Final major subdivision 12/7/06 - BoS conditionally approved final plan
|
Patriot Village Brad Miller & Louis Ferrone (PE)
|
North of Meco Road behind Miller residences and along Sullivan Trail
|
Was the Miller & Koegler farms. Originally proposed for 32 55 & older units to PC on 5/13/04. On BoS agenda 8/5/04. New plans are for 21 single family homes with a long drive from Meco between existing residences and under the power lines. Under engineer review 5/12/05. Still under review 6/9/05. Tabled by PC 7/14/05. PC tabled 8/11/05 when Hay said that his office is waiting for revised plans. On 9/8/05 the PC, in a 5:1 vote, granted Conditional Preliminary Plan Approval. Planner Eric Chuss cast the nay vote expressing concerns about 3 of the lots because they are under the power lines. The developer's representative said that the developer will not relinquish the lots and that "there's no science to support this concern." Solicitor Kline recommended that the Township get a sewer easement for its planned line to the planned bathroom in the adjacent recreation field. On the PC Agenda 1/12/06 for Final Major Subdivision. No one was there from the developer and the item was tabled. On 2/9/06, even though Chuss noted his concern about the proximity to power lines, the Final Major Subdivision was approved in a 6:1 vote. They agreed to everything in Hay's letter.
|
5/13/04 - PC new business 5/12/05 & 6/9/05 - PC - Hay said under review 7/14/05 - PC Preliminary Subdivision tabled. 8/11/05 - PC tabled 9/8/05 - PC Granted Conditional Preliminary Plan Approval 9/14/05 - BoS Granted Preliminary Plan Approval 1/12/06 - PC tabled Final Major Subdivision 2/9/06 - PC approved Final Major Sudivision 3/2/06 - BoS granted Final Plan Approval 6/15/06 - BoS accepted indemnification & sewer agreements
|
Kings Farm - A & B - also Kings Mill - See Kings Mill page for lawsuit news Kings Mill Development, LLC (Zawarski & Signature Homes)
|
Two major areas in the northern part of the Township, one going north from Padula Road and the other going north from Newlins Road E - Totals approx 380 acres.
|
There are two versions of this project in the works. The first involves approx. 800 dwelling units and was presented in non-public meetings to Staff and selected PC and BoS members. The second plan, conforming to the FP zoning shows 162 single family homes and was presented to the PC as a sketch plan on 7/14/05. Vito Tamborrino, PC Chair suggested that the developer return with both plans on 8/11/05. On 8/11/05 both sketch plans were presented to the PC for review. The PC voted 4:1 to deny recommending the 800+ home plan to the BoS. The atty for the developer said that the developer will take his case to the Supervisors. PC Chair Vito Tamborrino had hoped for a compromise plan and cast the "nay" vote. FYI, more than 300 residents attended this meeting! On 2/9/06 Atty. Benner once again addressed the PC, this time with a permitted "by-right" plan for 187 2 acre lots on 436 acres in the FP. There was much discussion and although there was no name calling, Turner noted the adversarial nature of the discourse. Without Hay's letter, Kline recommended to the PC that they should take no action at this time. It was tabled. On 7/13/06 armed with a three page letter from Hay and word that the developer has failed to be proactive regarding the "by right" plan submitted in February, the PC voted to reject the developer's offered time extension. Next stop for the conforming plan is the BoS. Read Nixon and Mausolf for more. On 7/20/06 the BoS heard: Hay state that he recommended accepting the time extension, Kline state that "good faith goes two ways," and Benner state, "We are going to prosecute this plan." At that the Board voted 4:0 to accept the offered time extension of 90 days. On 10/12/06 the PC acted on the recommendation of Hay to reject the "by right" major subdivision. Hay said that the developer has done nothing in answer to his July letter. He has done no perc tests. Tamborrino added that the developer "needs to show good faith." Tamborrino said too that it is "clear to me that they have no intention of going forward with this plan." Turner said that he thought it was "an abandoned plan." Solicitor Kline thought that the developer wants the Township to change its Act 537 Plan. Wideman was the sole voice to keep this plan alive. The vote to reject was 6:0 with Wideman abstaining because of the proximity of the land to his. On 10/19/06 the BoS accepted the developers' offer of a time extension. The developers' attorney was told that if the soil and perc tests are not done and completed plans submitted to the Township by 1/31/07, that this by-right plan will be rejected. Solicitor Kline also told the developers that if they are waiting for the Township to change its Act 537 plan which prohibits sewers in the FP, they can forget it. He added that the Township does not have capacity at the treatment plant. The time extension was granted in a 3:2 vote with Howell and Nicholas voting "nay." Read Nixon (Morning Call) for more. Kings Farm was back before the PC on 2/8/07 with yet another offer of a time extension this time until 7/31/07. The PC voted 7:0 to reject the time extension and also 7:0 to reject the by-right (under old zoning) plan. The perc tests are not complete and therefore the plan before the township engineer for review is not complete. The developers have had more than 1 year to finish the modules necessary for consideration. Read about it in Nixon and Lomax. It goes next to the BoS along with the PC's recommendations to reject. On 2/15/07, the BoS unanimously voted to reject the Kings Farm plan as an incomplete plan submission. This is the by-right plan allowed under the old zoning with 2 acre minimum lots in the FP district. According to Hay, the developer did not complete the soil test, did not submit a traffic study, etc. The developer's attorney confirmed that the plan submitted was incomplete and then stated that the Township should not have accepted an incomplete plan for review! He also said that this decision will be appealed. Read Lomax |